Gas pipelines’ relocation impedes N4.3bn Apapa road repairs –Dangote

Published

on

Despite the determination of the contractor to the deliver the project within the time frame, the relocation of gas pipelines and other facilities on the right-of-way of N4.3 billion Apapa-Wharf road reconstruction is slowing down the project, New Telegraph has learnt.

According to the Managing Director of AG Dangote Construction Company Limited, Mr. Ashif Juma, the gas pipes in the road’s Right of Way (RoW) had slowed down the project for over two months.

However, he stated that his company is on the top of the situation, pointing out that his firm has commenced relocation of gas pipelines slowing down the reconstruction of Apapa-Wharf road project.

Juma, while disclosing this to New Telegraph during a site inspection exercise in Lagos, said that the construction work has been divided into four sections.

New Telegraph, October 10, 2017

 

RipplesNigeria… without borders, without fears

Click here to join the Ripples Nigeria WhatsApp group for latest updates.

Join the conversation

Opinions

Support Ripples Nigeria, hold up solutions journalism

Balanced, fearless journalism driven by data comes at huge financial costs.

As a media platform, we hold leadership accountable and will not trade the right to press freedom and free speech for a piece of cake.

If you like what we do, and are ready to uphold solutions journalism, kindly donate to the Ripples Nigeria cause.

Your support would help to ensure that citizens and institutions continue to have free access to credible and reliable information for societal development.

Donate Now