Contractor: Why Dec Deadline for Lagos-Ibadan Rail Project May Not be Feasible
The contractor handling the Lagos-Ibadan standard gauge rail project, the Chinese Civil Engineering Construction Company (CCECC), has disclosed that the December 2018 deadline given by the federal government for the completion of the project might not be feasible if it fails to address the identified challenges.
A senior official of CCECC, who did not want to be named, disclosed to THISDAY that the project has been bedeviled with some huge challenges that are threatening the revised completion deadline for the project.
He said that beyond the two bridges that would be demolished in Lagos and rebuilt, several kilometers of gas, water pipes and telecoms cables would have to be relocated.
THISDAY, January 22, 2018
RipplesNigeria… without borders, without fears
Click here to join the Ripples Nigeria WhatsApp group for latest updates.
Join the conversation
Support Ripples Nigeria, hold up solutions journalism
Balanced, fearless journalism driven by data comes at huge financial costs.
As a media platform, we hold leadership accountable and will not trade the right to press freedom and free speech for a piece of cake.
If you like what we do, and are ready to uphold solutions journalism, kindly donate to the Ripples Nigeria cause.
Your support would help to ensure that citizens and institutions continue to have free access to credible and reliable information for societal development.