NERC to begin roll-out of meters May 1

Published

on

Electricity Regulatory Commission (NERC) has issued permits to meter asset providers (MAPs) to begin the roll out of new meters, effective from May 1.

This was disclosed in a statement on Saturday by NERC General Manager Public Affairs, Usman Arabi. It said that MAPs engaged by Abuja and Jos electricity distribution companies (DisCos) will install the new meters in customers’ premises within 10 working days of making payment.

Three firms engaged by Abuja DisCo are expected to supply 900,000 meters across its franchise areas, while the ones engaged by Jos DisCo will supply 500,000 meters.

On April 3, 2018, the NERC introduced the MAP regulation to new investors in the power sector to fast-track the roll-out of meters through the engagement of third-party investors.

READ ALSO: Relief as Senate orders Shell to pay Niger Delta communities N6.93bn

 “The Commission issued permits to Meter Asset Providers (MAPs) on 5th April 2019, in accordance with section 4(3) of the MAP Regulations 2018, to MAPs that were successful in the procurement conducted by Abuja and Jos Discos,” NERC said.

“Section 4(3) of the MAP Regulation 2018 requires all electricity distribution licensees to engage MAPs that would assist, as investors, in closing the metering gap and thus eliminating the practice of estimated billing in the Nigerian Electricity Supply Industry (“NESI”).

“AEDC has appointed Mojec International Limited, Meron Consortium and Turbo Engineering Limited to provide 487,000, 213,000 and 200,000 meters respectively while JEDC has appointed the Triple 7 and Mojec International Limited consortium to provide 500,000 meters.

“NERC has directed that the roll-out of meters shall commence no later than the May 1, 2019.”

The commission said it will monitor the roll-out plan of the firms to ensure that they comply with the regulation.

“Customers of AEDC, JEDC should expect from the take off of rollout date for meters to be installed in their premises within 10 working days of making payment to MAPs in accordance with section 18 (3) of the MAP Regulations 2018,” the commission said.

“MAPs shall charge a maximum of N36,991.50 for single phase meters and N67,055.85 for three phase meters. These costs are inclusive of supply, installation, maintenance and replacement of meters over its technical life.

“The Commission shall monitor closely the rollout plan of distribution licensees and overall compliance with the regulation and various service agreements by the MAP and electricity distribution licensees.”

Meanwhile, the latest third-quarter report by the commission released in January says out of the 8,310,408 registered electricity customers in the country, 4,606,106 don’t have meters and are subjected to estimated billing.

Join the conversation

Opinions

Support Ripples Nigeria, hold up solutions journalism

Balanced, fearless journalism driven by data comes at huge financial costs.

As a media platform, we hold leadership accountable and will not trade the right to press freedom and free speech for a piece of cake.

If you like what we do, and are ready to uphold solutions journalism, kindly donate to the Ripples Nigeria cause.

Your support would help to ensure that citizens and institutions continue to have free access to credible and reliable information for societal development.

Donate Now